【News】Two reports reveal environmental impacts of Kobe’s coal power plants
Kobe Steel submitted the post-monitoring survey report on the Kobe Power Station Units 3 and 4 installation project (FY2022)” to Hyogo Prefecture.
-
【News】Judicial decision on Kobe coal-fired power stations: Japan lacks urgency on the climate crisis
Two court cases concerning Kobe Power Plant Units 3 and 4,built and operated by Kobe Steel, Ltd. concluded in March 2023, but the civic battle continues.
-
【News】Kobe Unit 4 begins commercial operation – civil lawsuit ruling coming March 20
On February 1, Kobe Unit 4 started its commercial operation. Two lawsuits filed against the construction and operation of Units 3 and 4 are still ongoing.
-
【News】Kobe Climate Case: Court Again Rejects Plaintiffs’ Administrative Lawsuit
On April 26, 2022, an appeal court ruling was handed down in the Kobe Climate Case administrative lawsuit. Unfortunately, the citizens’ lawsuit was dismissed by the court, directly affirming the ruling of the first trial.
-
【News】Kobe Power Station Unit 3 Begins Commercial Operation
On February 1, 2022, Kobe Power Station Unit 3 (650MW), which had been undergoing trial operation since last year, began commercial operation, with expected CO2 emissions of 3.46 million tons per year.
-
【News】 Kobe Climate Case: Administrative Lawsuit Concludes
On December 14, the appeal in the administrative lawsuit challenging the government’s responsibility in approving the construction of two additional coal-fired power plants (total capacity 1,300 MW) at the Kobe Steel Works concluded. The verdict will be rendered on Tuesday, April 26, 2022, at 2:30 p.m. at the Osaka High Court.
-
【News】Action Report: KOBELCO General Meeting of Shareholders 2021
On June 23, No Coal Kobe, a local community group working to stop construction of coal-fired power plants in Kobe, attended KOBELCO’s General Meeting of Shareholders and organized a protest outside the venue. Here are the questions and answers regarding coal-fired power.
-
【News】Despite ongoing court cases, Kobe Steel’s Coal-fired Power Plant Unit 3 fires up boiler
Despite construction being disputed in two ongoing court cases, on May 5, Kobe Steel’s Coal-fired Power Plant Unit 3 finished its construction and progressed further with the firing of its boiler.
-
【News】Kobe Climate Case Judicial Ruling: Voices of Citizens Not Heard
On March 15, the ruling was announced in a court case by local citizens seeking to stop the construction of two Kobe Steel coal-fired power units in Kobe City.
-
【News】Kobe Climate Case court hearing finishes: Judgment on government’s responsibilities expected March 15, 2021
The final hearings in Osaka District Court (presiding judge: Kenichi Mori) finished on January 20, 2021, as pa…
-
Construction Continues on Units 3 and 4 of Kobe Steel’s Coal-fired Power Plant
A local organization captures on video the state of construction of Units 3 and 4 of Kobe Steel’s coal-fired p…
-
Patients with pollution-related illnesses meet with Kobe Steel to discuss coal-fired power plant
(By Toshiyuki Ueda, Nishiyodogawa Patients and Family of Pollution-Related Diseases Association) “We want pati…