【Update】Japan Coal Plant Tracker: 20181225


This is up date on December 25th.

【Proposal】

・Akita Port No.1 , No.2 (tentative)  METI released confirmation document of EIA on December 20.
METI’s document(PDF)

・Kaita power station(112MW)The name of the power plant is fixed and its construction started on December 11.

・Misumi No.2  It announced construction would be started on December 1, had ceremony on November 1.

・Yokosuka  JERA submitted Final EIS document on November 15, METI issued confirmation document on November 30.
METI(link
Final EIS deocument(link

【Exisiting】

Information of turbine steam pressure and steam temperature of each plants are updated.