We have checked our list of domestic coal-fired power plants that are slated to be built, under the bidding process and that have been shutdown.
It is good to know no new one comes at this moment, and the total number is remaining as 48 with a combined capacity of 23,496MW.
Please check back with us for updates!
This list is updated monthly.The Newest one is on Additional information page.
“List of coal power plant plants, bids, shutdown” (Research by Kiko Network, * last updated August 3rd,2015) (★: Updated)
September 3rd updates
[[ Plans ]]
+++ Updates of the status +++
* No.1 Suzukawa Energy Center (add the name of the project operation company)
* No.2 Nakayama Nagoya (Started construction)
* No.37/No.38 Nakoso and Hirono in Fukushima (Tokyo Electric Power, Mitsubishi Heavy Industries, Ltd., Mistubishi Corporation, Mitsubishi Electric Corporation, Joban Joint Power Co., Ltd. have established Fukushima Revitalization Power Consortium.)
* No.39 Ichihara Thermal Power Generation Godo Kaisha (add the name of the project operation company, and fixed the date of starting operation.)
[[ Bidding ]]
+++ Updates of the status +++
* No.2 Tokyo Electric Power’s 6000MW bidding is concluded (5 successful bids of 1450MW in total).
** we once updated the list on Sep. 1st, and updated it again on Sep. 3rd, because we got some big news in these days.