【Update】Japan Coal Plant Tracker: 20180517


This is update on May 17th.

▷(tentative)Yokosuka Power Plant, No.1, No.2
2018/4/19 JERA submitted the business operator’s opinion to the governor of Kanagawa prefecture.
(in Japanese) http://www.pref.kanagawa.jp/docs/ap4/cnt/f247/documents/ikenkennkai.pdf

▷(tentative)Soga Coal Power
2018/5/10 The mayor of Chiba city submitted the opinion paper regarding to the EIA Screening to the governor of Chiba prefecture.
(in Japanese )https://www.city.chiba.jp/kankyo/kankyohozen/hozen/documents/assess-example-sogakaryoku-houhousyo.pdf

▷Kobe Works New (tentative) -No.1, No.2
2018/5/11 The KOBELCO power Kobe submitted the Draft EIS (DE) .
(in Japanese )http://www.kobelco.co.jp/notices/1199377_15586.html